• 2018 - 2021 Norilsk-Taimyr Energy Company Norilsk Thermal Power Plant Station No. 2, Krasnoyarsk Territory

     

    Set of construction works as part of reconstruction

     

     

    TASKS

     

    • Works were carried out to deinstall and install wall railings of the Norilsk Thermal Power Station No. 2, main building in axes A/1-10, D/3-10, 1/A-B-V, 3/V-G-D according to the project "Thermal Power Station No. 2.
    • Reconstruction (Replacement) of Equipment in the Energy Units of Station 1 and Station 2";
    • Delivery of works regarding application of anticorrosion and fireproofing coating to metal structures in the main facility.

       

FEATURES

  • Difficult logistics in conditions of the Russian Far North;
  • The equipment was reconstructed without any suspension of the Thermal Power Station operation;
  • Simultaneous operation with other contractors;
  • Exposure to severe conditions during the application of protective coating to surfaces;
  • Industrial climbers carried out most of the works.